Fault Analysis of Diesel Generator Fuel Supply Time Too Early or Too Late

Time:2023-10-11

When the diesel generator set starts and starts running, the problem of poor operation may be due to fuel supply problems, such as early or late fuel supply, insufficient fuel supply, etc. To avoid such situations, it is necessary to maintain the diesel generator set carefully and strictly.

(1) Reasons for premature fuel supply time:

① The fixing screws of the connecting plate of the coupling are loose and displaced (this reason will cause the total oil supply time to be too early);

② Improper adjustment or movement of the adjustment screw on the fuel injection pump plunger;

③ Individual oil outlet valves are not tightly closed.

When the fuel supply time is too early, there is a rhythmic and crisp metallic knocking sound inside the cylinder, making it difficult to start. The diesel engine works poorly, lacks power, emits white smoke from the exhaust, and has a smell of "raw oil". It is easy to stop at low speeds.

When checking, the high-pressure oil pipe of the first cylinder can be removed, the crankshaft can be rotated, and attention should be paid to observing the oil level in the tight seat of the oil outlet valve on the fuel injection pump. At the moment when the oil level just fluctuates, check whether the fuel injection advance angle of the diesel engine meets the regulations from the fuel supply timing line on the flywheel and the mark on the flywheel housing. If it does not meet the requirements, it should be readjusted. If necessary, check cylinder by cylinder again.

(1) The reason for the delayed fuel supply time:

① The fixing screws of the connecting plate of the coupling are loose and displaced;

② Improper adjustment or movement of the adjustment screw on the fuel injection pump plunger;

③ Excessive wear on the driving gears, tappets, camshafts, plungers, and sleeves of the fuel injection pump.

When the fuel injection time is too late, the diesel engine is difficult to start. After starting, there is a low and unclear knocking sound in the cylinder. The speed of the diesel engine cannot increase with the increase of the throttle, resulting in high engine temperature, decreased power, increased fuel consumption, and black smoke. The inspection method is the same as checking for premature fuel supply time.

Guangzhou Saiwei Energy Technology Co., Ltd. is a comprehensive enterprise specializing in design, production, and generator installation. Guangzhou Saiwei has many years of experience in engineering design and installation services. For many years, Guangzhou Saiwei has been committed to providing every customer with comprehensive products and energy solutions, including technical consulting, whole machine and generator supply, operation training, etc., with leading technology and first-class quality. The product range covers land diesel generator sets, marine generator sets, high-voltage generator sets, etc., and is widely used in industries such as power, communication, iron towers, healthcare, financial systems, data centers, etc. Welcome to inquire: 13302262088